University of Missouri - Columbia

Procurement Services

 

Columbia Campus Procurement

 

Procurement Guidelines

 

Table of Contents

 

Methods of Procurement

Procurement Limitations and Requirements

Estimated Processing Times for Procurement Activities

 


 

Procurement Services assists departments in acquiring goods and services:

 

Go to top of page

 

Methods of Procurement

 

Items and services obtained from external sources should be procured in an appropriate manner, using either a University Purchasing Card or Purchase Order. Reference the Payment Method for Expenditures - Quick Reference Guide for a summary list of various items/services and the appropriate procurement method to utilize for each.

 

Go to top of page

 

Procurement Limitations and Requirements

 

The following requirements apply to University purchases, based on the total cost of the item or service:

 

Go to top of page

 

Procurement Limitations and Requirements

 

Process Description #Business Days
Sourcing a purchase order from a valid requisition 1-3
Processing an informal bid request (from receipt of specifications to summary of bid results) 15-30
Sending purchasing card applications to the bank for processing 1-2
Completing purchasing card change forms within 24 hours
Responding to Form 27 requests for pick-up of surplus property 5-7
Tagging of capital assets upon notification of readiness 5-7

 

 